Envision Hands Over Initial 120 MW at Ulanqab Data Center Campus

DataNews Editorial Team

Envision has handed over the initial 120 MW phase of its Xinghe data center campus in Ulanqab, Inner Mongolia, following customer acceptance in August 2026, according to the source. The campus is planned as a four-phase development with up to approximately 800 MW of IT capacity.

Highlights
  • The reported customer handover covers an initial 120 MW phase, not the full planned campus.
  • Xinghe is planned for up to approximately 800 MW of IT capacity across four phases.
  • The first two phases are associated with approximately 240 MW of load, 420 MW of wind capacity and four-hour energy storage.
  • Envision is piloting a 5 MW 10 kV AC-to-800 V DC rack-power architecture using a solid-state transformer.
  • Grid interconnection, balancing resources and land availability remain key execution constraints.

Envision has completed customer handover of the first 120 MW of data center capacity at its Xinghe campus in Ulanqab, Inner Mongolia, according to the source. Customer acceptance took place in August 2026.

Xinghe is planned as a four-phase campus with up to approximately 800 MW of IT capacity. That figure is a development target for the full campus, rather than commissioned capacity: the reported handover applies only to the initial 120 MW phase. Separately, the source refers to 3 GW as Envision’s broader data center portfolio across Inner Mongolia, not as capacity at the Xinghe campus.

The power architecture is intended to integrate generation, storage, grid connection, substations and data halls. For the first two phases, representing approximately 240 MW of data center load, the source describes two associated wind farms with combined installed capacity of 420 MW and four-hour energy storage. The plan is for proprietary wind generation to cover more than 60% of electricity consumption for those two phases; this remains a future target rather than demonstrated operating performance.

Envision is also testing a 5 MW data hall power design using a solid-state transformer to convert 10 kV AC input to 800 V DC for racks. The source does not establish the economics of this approach and notes that the equipment currently costs more than conventional alternatives.

The source estimates construction cost for the initial facilities at about one-fifth of comparable US projects. That comparison should be treated cautiously, as the scope of works and the inclusion of engineering systems and IT equipment can differ materially between projects. It also cites roughly four months from the start of land procedures to construction and 10–11 months from construction start to customer acceptance, while stating that the tenant required delivery within six months.

If the stated build-out and power configuration are realised, the project could offer a test case for co-designing AI-oriented data center capacity with renewable generation and storage. However, its execution remains dependent on timely grid interconnection, balancing resources, storage deployment and land availability.

Why It Matters

The project combines data center capacity with planned wind generation, energy storage, grid interconnection and associated electrical infrastructure. If delivered as outlined, this model could sharpen competition among AI data center clusters on time-to-power and electricity costs, while underscoring that reliable grid access and balancing capacity remain essential for continuous-load facilities.