Finnish Regulator Halts Preparatory Work on Google Data-Center Sites in Muhos and Otanmäki
DataNews Editorial Team
Finland’s LVV regulator has required Google to halt work associated with two planned data-center projects in Muhos and Otanmäki after forest clearance took place before the required environmental assessment was completed. Google said it stopped preparatory work after receiving the regulator’s 6 October letter and would comply with the requirements.
- LVV required a halt to work associated with Google’s planned Muhos and Otanmäki data-center projects after forest clearance preceded completion of a required environmental assessment.
- Google says it stopped preparatory work after the regulator’s 6 October letter; no cancellation of either project has been reported.
- About 330 hectares were cleared at Muhos; Google plans tree planting across 130 hectares there.
- Google’s at-least-€13 billion two-year AI and data-center infrastructure plan is not allocated specifically to these Finnish sites.
- The case could increase permitting, environmental-monitoring and community-engagement requirements for new Finnish data-center developments.
Finland’s LVV regulator has ordered a halt to work connected with Google’s planned data-center sites in Muhos and Otanmäki, in the Kajaani area, following forest clearance before completion of a required environmental assessment.
Google said it halted preparatory activity at the Muhos and Kajaani-area sites after receiving LVV’s letter on 6 October. The company apologised for the clearance, said it had submitted a formal response to the regulator, and stated that it was taking measures to protect water quality. The reported stoppage applies to preparatory work; the available information does not indicate that either project has been cancelled or that operating data centers have been affected.
At Muhos, approximately 330 hectares of forest were cleared for the data-center site, affecting an estimated 250,000 trees. Google has said it plans to plant trees on 130 hectares in Muhos. At Otanmäki, an expert from the Finnish Association for Nature Conservation estimated that around 150,000 trees were cleared; this is an external estimate rather than a regulator-established figure.
The two Finnish sites are included in Google’s announced plan to invest at least €13 billion in AI and data-center infrastructure over the next two years. That figure is a company-wide announced investment plan, not confirmed spending, and the available information does not allocate any portion of it to the two Finnish projects.
For data-center developers and investors, the case highlights permitting as a material early-stage execution issue. Environmental due diligence, water-quality and runoff controls, and engagement with local communities may need to be addressed before site preparation begins. In Finland, where 145 new data centers are reportedly at various planning stages, these requirements could extend site-development schedules and raise delivery risk for large AI-oriented projects. The event alone does not establish any change to Google’s investment commitment or the ultimate scale of the two projects.
The case illustrates how environmental permitting, water-risk management and local opposition can delay site development for large AI data-center projects, including in markets seeking such investment. It could lead to more stringent environmental documentation, runoff monitoring and earlier community engagement in Finland, increasing development timelines and execution risk for new campuses.
- — / October 27, 2026 · ChineseSource →
This article was prepared by the DataNews editorial team based on the sources listed above.