Getworks completes liquid-cooled NVIDIA HGX B300 rack deployment at Yuzawa GX Data Center
DataNews Editorial Team
Getworks has completed deployment of its IR7044 liquid-cooled rack solution at the containerised Yuzawa GX Data Center in Yuzawa, Niigata Prefecture, Japan. The rack integrates eight Dell PowerEdge XE9780L GPU server nodes based on NVIDIA HGX B300 and a Schneider Electric Motivair MCDU-10 coolant distribution unit.
- Getworks completed an eight-node Dell PowerEdge XE9780L deployment using NVIDIA HGX B300 at Yuzawa GX Data Center.
- The IR7044 rack is installed in a 21-inch ORv3 configuration and uses direct liquid cooling through cold plates.
- The eight GPU server nodes are stated to consume 106 kW of IT power.
- A Schneider Electric Motivair MCDU-10 CDU is reported to handle approximately 85% of heat from the eight-node configuration.
- The cluster uses Dell PowerSwitch Z9864F networking with SONiC.
Getworks has completed installation of its IR7044 liquid-cooled rack solution at the Yuzawa GX Data Center, a containerised facility that it operates in Yuzawa, Niigata Prefecture, Japan. The deployment uses Dell Technologies PowerEdge XE9780L servers built around NVIDIA HGX B300.
The IR7044 rack contains eight XE9780L server nodes in a 21-inch ORv3 rack format. Each server is equipped with eight NVIDIA HGX B300 chips and uses direct liquid cooling via cold plates. Getworks states that the eight-node GPU server configuration consumes 106 kW of IT power.
Cooling liquid is distributed by a Schneider Electric Motivair MCDU-10 CDU. According to Getworks, the CDU handles approximately 85% of the heat generated by the eight GPU server nodes. This figure describes the share of server heat handled through the CDU liquid-cooling system, rather than overall cooling efficiency or facility-level PUE or WUE.
The GPU cluster uses Dell PowerSwitch Z9864F networking with SONiC. The combination of dense GPU compute, direct liquid cooling and dedicated network fabric illustrates the infrastructure integration required for AI-oriented rack deployments in containerised environments.
The installation may indicate a growing role for pre-integrated AI infrastructure in the containerised data-center segment. For operators and suppliers, such deployments could place greater emphasis on power-density engineering, liquid-loop design, leak monitoring and GPU-cluster networking. Getworks has not disclosed the site’s total IT capacity, number of racks, CAPEX, PUE, commissioning date or end user of the compute cluster.
The deployment provides a practical example of direct liquid cooling for high-density AI infrastructure in a modular containerised data-center environment. It underscores that GPU racks of this class require coordinated integration of compute, DC power, liquid-cooling loops and low-latency network fabric; however, the disclosed information does not allow the deployment’s broader market impact to be quantified.