Giga Energy Signs US$1bn Lease for 60MW Project Clay Data Center Under Construction in Texas
DataNews Editorial Team
Giga Energy has signed a 10-year, US$1bn lease with an undisclosed US-based AI cloud provider for its 60MW Project Clay data center, which is under construction in Hunt County, Texas. The company plans to develop, own and operate the campus, with readiness for service targeted for spring 2027.
- Giga Energy signed a 10-year, US$1bn lease with an undisclosed US-based AI cloud provider.
- The lease covers the 60MW Project Clay data center under construction in Hunt County, Texas.
- Giga Energy plans to develop, own and operate the campus; readiness for service is targeted for spring 2027.
- Project Clay is planned to use GigaBase modular infrastructure and fully closed-loop cooling.
- The stated power approach relies on available capacity from dedicated county energy infrastructure rather than distribution capacity serving existing customers.
Giga Energy has executed a 10-year lease valued at US$1bn with an undisclosed US-based AI cloud provider for Project Clay, a 60MW data center project under construction in Hunt County, Texas.
Giga Energy plans to develop, own and operate the campus for the customer. The facility is scheduled to be ready for service in spring 2027. The 60MW figure is described as project capacity; the available information does not specify whether it refers to IT load, total facility power or another capacity measure.
Project Clay also marks the formal introduction of GigaBase, Giga Energy’s modular AI data-center system. The campus is planned with a fully closed-loop cooling system that, according to the company, will not rely on municipal or groundwater supplies.
Its power design is intended to use available capacity from dedicated energy infrastructure in the county rather than distribution capacity serving existing homes and businesses. This is a company claim and has not been independently technically verified in the available source.
The campus covers around 30 acres. Giga Energy expects the build phase to support around 300 construction jobs, followed by 24 permanent full-time roles once the site is operational.
For the wider market, the transaction could indicate the value of pre-leasing specialized AI infrastructure before delivery. The project’s emphasis on modular architecture, closed-loop cooling and dedicated energy infrastructure also suggests that deployment speed and the management of local grid and water impacts may be increasingly important in AI data-center development.
The agreement secures AI-cloud demand for capacity still under construction through a long-term lease. It also illustrates how developers are positioning modular deployment, dedicated power infrastructure and closed-loop cooling as responses to grid-access and water-resource constraints.
- Data Centre Magazine / November 18, 2026 · EnglishSource →
This article was prepared by the DataNews editorial team based on the sources listed above.