Google Signs 50 MW Geothermal PPA With Quaise for Oregon Project

DataNews Editorial Team

Google and Quaise Energy have signed a 50 MW power purchase agreement for ultra-high-temperature geothermal generation from Project Obsidian in central Oregon. Deliveries are expected no earlier than 2030 for Google’s existing data centers in The Dalles and the local community.

Highlights
  • The agreement is a 50 MW PPA for future geothermal supply, not an operating Project Obsidian asset.
  • Power deliveries are expected no earlier than 2030.
  • The contracted power is intended for existing Google data centers in The Dalles and the local community.
  • Project Obsidian’s initial phase is planned to use conventional drilling; millimetre-wave drilling is planned for a later phase.
  • Key commercial and development details, including pricing, term, CAPEX, permitting and total project output, were not disclosed.

Google has agreed to procure 50 MW of ultra-high-temperature geothermal power from Quaise Energy’s Project Obsidian in central Oregon. The PPA covers future electricity supply rather than operating generation capacity, with deliveries expected no earlier than 2030.

The power is intended to serve Google’s existing data centers in The Dalles as well as the local community. The agreement does not disclose the PPA term, electricity price, Project Obsidian CAPEX, permitting status, total project output, or the precise share of the contracted 50 MW that would directly serve data-center load.

Project Obsidian is planned as a phased development. Its first phase is expected to use conventional drilling for commercial generation. A later phase is planned to deploy millimetre-wave drilling technology; this does not indicate that the technology has already been implemented at the site. Quaise expects Project Obsidian to become the first geothermal project globally to use millimetre-wave drilling.

For data-center power procurement, the deal is a potential example of diversification toward firm low-carbon generation. If the project proceeds on schedule, it could expand options for contracting around-the-clock low-carbon electricity, while illustrating how hyperscaler demand may support the commercialisation of earlier-stage geothermal technologies. The technology and delivery timetable, however, carry greater risk than established operating generation assets.

Google has three data-center campuses in Oregon, where the reported share of carbon-free energy has reached 83%. Other geothermal arrangements involving Google, including agreements with Fervo Energy, NV Energy and Baseload Capital, are separate projects and should not be treated as capacity associated with Project Obsidian.

Why It Matters

The agreement signals large data-center operators’ interest in firm, around-the-clock low-carbon power beyond variable renewables. If delivered on the indicated timetable, it could broaden the range of clean-power contracting models available to data-center loads while supporting early commercialisation of ultra-high-temperature geothermal technology.

Sources

This article was prepared by the DataNews editorial team based on the sources listed above.