IEA projects 120GW of additional data-center capacity by 2030 as AI drives power demand

DataNews Editorial Team

Data Centre Magazine — article illustration
Image source: Data Centre Magazine

The International Energy Agency projects that global data-center electricity consumption will double to 1,000TWh by 2030 under its STEPS scenario, alongside a further 120GW of capacity. The agency also forecasts US$4 trillion in data-center-related investment by 2030, with AI-optimised infrastructure accounting for most of the planned capacity growth.

Highlights
  • The IEA’s STEPS scenario projects data-center electricity consumption of 1,000TWh by 2030.
  • Global aggregate data-center capacity is estimated at 120GW today, with another 120GW projected by the end of the decade.
  • More than three-quarters of planned additional capacity is intended for AI-optimised servers.
  • The IEA forecasts US$4 trillion in additional data-center-related investment by 2030.
  • Grid interconnection queues and supply-chain constraints could limit or redirect project delivery.

The International Energy Agency’s World Energy Outlook 2026 projects a substantial expansion of global data-center infrastructure through 2030, led by AI-oriented deployments. Under the STEPS scenario, sector electricity consumption is expected to double to 1,000TWh by 2030, while an additional 120GW of data-center capacity is projected by the end of the decade.

The IEA puts the current aggregate capacity of all data centres globally at 120GW. More than three-quarters of the forecast additional capacity is intended for AI-optimised servers. The agency also reports that the stock of accelerated servers has grown 18-fold since 2020, underscoring the shift in the sector’s demand profile toward compute-intensive workloads.

Investment requirements are correspondingly large. The sector attracted US$565 billion in investment in 2025, when its electricity consumption rose 17%, according to the reported IEA assessment. The agency forecasts a further US$4 trillion in data-center-related investment by 2030.

The existing capacity base remains geographically concentrated: nearly 80% is located in China, the European Union and the United States. The IEA flags a growing mismatch between prospective data-center development and local power-system capacity. In Denmark, Finland, Northern Virginia and Texas, prospective data-center capacity exceeds the current peak load of the respective power systems.

The agency is also using satellite imagery to monitor 93 large AI factories. Their inferred potential capacity increased tenfold over 24 months to 17GW; once construction is complete, their combined capacity is projected to reach about 50GW. These figures are not a measure of confirmed operating capacity.

For operators, utilities and infrastructure investors, the outlook suggests that grid interconnection, power equipment and supply-chain availability may increasingly determine which projects progress. The IEA cautions that interconnection queues in some jurisdictions run for years and that not all prospective capacity will be built. As a result, the forecast may favour markets able to provide power availability, timely grid connections and flexible demand or supply arrangements.

Why It Matters

The outlook frames AI infrastructure as a combined data-center, IT-equipment and power-infrastructure buildout. It also highlights grid interconnection and supply-chain constraints as potential limits on delivery, increasing the importance of markets with available power, faster connection processes and flexible load or on-site supply options.