IEA projects another 120 GW of global data-center capacity by 2030, led by AI

DataNews Editorial Team

Image source: primary source

The IEA projects that global data-center capacity could add about 120 GW by 2030, roughly matching its estimate of approximately 120 GW today. AI facilities are expected to account for around 75% of the projected increase, making power availability and grid delivery central constraints on new capacity.

Highlights
  • The IEA projects about 120 GW of additional global data-center capacity by 2030.
  • AI facilities could account for roughly 75% of the projected capacity increase.
  • Ninety-three large AI computing facilities are reported to be under construction or expansion, with about 17 GW of combined power supply capacity.
  • Grid build-out timelines and shortages of turbines and components could delay delivery of new AI data-center loads.
  • The projected expansion could intensify competition for secured power capacity and grid interconnections.

The IEA’s World Energy Outlook 2026 projects a substantial expansion in global data-center capacity, with approximately 120 GW of additional capacity expected by 2030 on top of an estimated current global total of about 120 GW. Around 75% of the expected new capacity is associated with AI facilities.

The agency identified 93 large AI computing facilities that are under construction or being expanded. Their combined power supply capacity has increased from less than 2 GW to approximately 17 GW over two years. Once fully completed, these facilities could require about 50 GW of electricity. That figure is a future conditional estimate, rather than current consumption.

The central delivery risk is not solely data-center construction. The IEA points to the ability of power systems and generation-equipment supply chains to connect and supply new loads on time. Renewable-generation projects typically take one to five years to complete, while transmission infrastructure may take three to five times longer. Shortages of gas turbines and other components could create further constraints.

The supply mix presents a separate challenge. Nearly half of data-center-related power purchase agreements are linked to renewable generation, but coal and natural gas account for about 60% of actual data-center electricity consumption, according to the cited estimates. The IEA expects emissions associated with data-center use of coal and gas to rise by 70% by 2030.

For operators, hyperscalers and investors, the forecast suggests that competition could increasingly centre on firm energy capacity, grid interconnection and scarce generation equipment. This could increase the strategic value of projects with power already secured and potentially support greater use of self-generation, although such strategies remain dependent on constrained turbine and component supply. The scale of new demand could also heighten public opposition and tariff risks where network and generation costs are passed through to wider customer groups.

Why It Matters

If the forecast is realised, confirmed power supply, grid interconnection and access to generation equipment could become more decisive than site availability or compute hardware in determining AI data-center delivery. Projects with secured energy capacity may gain in value, while on-site generation remains exposed to shortages of turbines and related components.