Power and turbine constraints could redirect part of AI data-center demand toward Asia
DataNews Editorial Team
A Chinese industry publication, citing Morgan Stanley forecasts, argues that power availability, grid interconnection queues and gas-turbine supply are becoming binding constraints on AI data-center expansion, particularly in North America. The review suggests that some demand could shift toward Asian markets with more accessible generation and power infrastructure.
- The review projects US data-center electricity demand of 97 GW by 2028, alongside a potential shortfall of about 70 GW.
- Grid interconnection queues may delay new generation and storage projects for around five years on average, and eight to 12 years in key markets.
- Global gas-turbine demand is forecast at 129 GW by 2028, compared with expected supply of about 87 GW.
- The US$7.6 trillion estimate for 2026–2031 combines global data-center and energy-infrastructure CAPEX.
- Any shift of AI data-center demand from North America to Asia remains a market inference rather than an announced project pipeline.
A Chinese industry review citing Morgan Stanley forecasts has highlighted emerging constraints in electricity supply, grid interconnection and generating-equipment availability for AI data centers. The article focuses primarily on North America, where power-system limitations could restrict the pace of new data-center development and potentially redirect part of demand to Asia.
According to the projections cited by the publication, US data-center electricity demand could reach 97 GW by 2028, with a potential power shortfall of about 70 GW. These are forecasts rather than figures for operating capacity or completed grid connections.
Grid interconnection is presented as a central bottleneck. The article says that about 2,600 generation and storage projects are awaiting connection, with an average wait of around five years from interconnection application to commercial operation. On key markets, it says, the process may take eight to 12 years. Such timelines could limit the availability of new supply for large AI load clusters even where generation projects have been proposed.
The review also points to a prospective shortage of gas-turbine capacity. It forecasts global demand for gas turbines of 129 GW by 2028, against expected supply of about 87 GW. This potential gap could affect data-center operators and power developers considering gas-fired generation as part of their power strategy.
For the broader buildout, the publication estimates combined global capital expenditure on data centers and power infrastructure at about US$7.6 trillion over 2026–2031, including US$765 billion in 2026. The figures combine IT and energy-infrastructure spending and do not provide a split between the two categories.
The article identifies Asia as a potential recipient of demand constrained by power and grid infrastructure in North America. It names Gulf Development, Adani Power, SDI and China Yangtze Power among companies that may be associated with meeting AI data-center energy demand in Asia, but provides no evidence of specific AI data-center contracts or commissioned projects involving them.
If the cited forecasts materialise, power capacity, interconnection access and turbine procurement could become key determinants of AI data-center delivery schedules. This could support greater investment in dedicated generation, storage and grid infrastructure, while favouring locations where power can be secured on more practical timelines.
The analysis frames power delivery—not only compute hardware—as a potential determinant of AI data-center deployment schedules. If these projections materialise, access to generation, grid connections and gas-turbine equipment could influence project geography, capital allocation and the use of dedicated power and storage assets.