Power availability constrains South Korea data-center supply as AI demand rises, CBRE Korea says
DataNews Editorial Team
AI-driven demand for data centers in South Korea is rising sharply, but power availability has become the principal constraint on new supply, according to CBRE Korea. Of 522 data-center grid-impact assessment applications in the Seoul metropolitan region, only 10—1.9%—completed formal review.
- CBRE Korea identifies power availability as the main bottleneck for new data-center supply in South Korea.
- Only 10 of 522 Seoul metropolitan-region data-center grid-impact assessment applications passed formal review.
- High CAPEX requirements and rapid AI-chip refresh cycles are additional constraints on investment decisions.
- Existing facilities with secured power, sites and quality tenants may benefit if new supply remains limited.
- CBRE Korea is advising global AI-focused cloud companies considering the South Korean market.
South Korea’s data-center market is facing a widening gap between AI-led demand and the availability of power required to support new development, according to CBRE Korea.
In an interview with Maeil Business Newspaper, Lim Dong-soo, head of CBRE Korea, identified power procurement as the largest obstacle to new data-center supply. High capital requirements and the rapid turnover of AI-chip generations are also weighing on investment decisions, he said.
The constraint is evident in grid-impact assessment activity in the Seoul metropolitan region. From August 2024 through March of the current year, 522 data-center applications were received for assessment of their impact on the power system. Only 10 applications, or 1.9%, passed formal review.
CBRE Korea said the limited availability of new power-backed sites is increasing the value of existing high-quality data centers that already have secured electricity supply, a site and quality tenants. Such facilities are signing lease agreements at rates above those initially expected during development, according to the firm.
The market implication is that access to grid capacity may increasingly function as a scarce asset alongside land and customer relationships. This could limit the rate of new data-center construction and support the pricing and lease rates of operating assets with confirmed power supply. It could also increase the importance of securing grid interconnection early in the development process.
CBRE Korea is also advising global AI-focused cloud companies considering entry into the South Korean market, indicating continued interest from prospective demand-side participants. The source does not identify those companies or provide project capacities, investment values or specific development plans.
The figures suggest that grid infrastructure could determine the pace of new data-center capacity delivery in South Korea. If new supply remains constrained, existing facilities with secured power, suitable sites and established tenants could command stronger rental value, while early grid-interconnection planning may become more important for new developments.