Rowan secures more than $1.5 billion in corporate financing for US hyperscale data-center pipeline

DataNews Editorial Team

Image source: primary source

Rowan Digital Infrastructure has secured more than $1.5 billion in new corporate-level financing to support early-stage development of its US hyperscale data-center campus pipeline. The facilities are intended to fund land acquisition, power procurement and long-lead equipment orders.

Highlights
  • Rowan has secured more than $1.5 billion in new corporate-level financing for US data-center development.
  • The package includes a $600 million term-loan upsize, plus $945 million of revolving-credit and letter-of-credit capacity.
  • Funding is designated for early-stage development needs, including land, power and long-lead equipment.
  • Rowan reports a 5.5 GW US project pipeline and more than 1.2 GW of contracted capacity, neither of which confirms operational capacity.
  • The company cites Green Finance Framework funding for two 300 MW campuses: Temple and Cinco in Medina County, Texas.

Rowan Digital Infrastructure has arranged more than $1.5 billion in new corporate financing for the development of its US hyperscale data-center campus platform.

The package includes a $600 million upsize to the company’s holding-company term loan, led by Apterra Infrastructure Capital. The increase expands Rowan’s existing corporate credit facility with Apterra to $900 million. Rowan also arranged a $590 million revolving credit facility and a $355 million letter-of-credit facility, both led by Citibank, N.A. Together, the latter two facilities provide $945 million of revolving and letter-of-credit capacity.

The company said the financing will support early-stage pipeline development, including land acquisition, securing power and ordering long-lead equipment. The revolving facility includes an accordion feature that could increase borrowing availability to as much as $2 billion.

Rowan states that it has a 5.5 GW project pipeline across multiple US markets, with more than 1.2 GW contracted to technology leaders. These figures describe the company’s pipeline and contracted capacity; they do not establish that the associated projects are under construction or operational, and Rowan has not disclosed the relevant sites, delivery dates, construction status or contract terms.

The company also said it has secured $4.4 billion under its Green Finance Framework across three projects. This includes nearly $3 billion for its 300 MW Temple campus and $550 million for its 300 MW Cinco campus in Medina County, Texas.

Corporate revolving facilities and letters of credit can give large data-center developers flexible funding for site preparation and power-related obligations without requiring separate financing for each asset. For a developer with a stated 5.5 GW pipeline, this could intensify competition for developable land, grid interconnections and long-lead equipment in US markets.

Why It Matters

The financing expands Rowan’s liquidity for development activities that often determine whether large data-center campuses can advance, particularly site control, grid-related power commitments and equipment procurement. It could help move portions of the company’s stated pipeline toward execution, but the transaction does not confirm new capacity has entered construction or operation.