SK Telecom and Hyosung Heavy Industries Sign MOU for Gigawatt-Class AI Data Center Infrastructure
DataNews Editorial Team
SK Telecom and Hyosung Heavy Industries have signed a strategic memorandum of understanding covering power infrastructure preparation for gigawatt-class AI data center projects. The partnership includes supply coordination for critical 345 kV substation equipment, joint work on 800 V DC distribution, and the pursuit of new AI data center opportunities.
- SKT and Hyosung Heavy Industries have signed an MOU, not a project construction or equipment-supply contract.
- The partners will coordinate supply of critical equipment for 345 kV substations, including long-lead items.
- Joint work will cover evaluation and demonstration of 800 V DC distribution.
- SKT’s previously announced target is up to 15 GW of aggregate AI data center development by 2035.
- The agreement may help address procurement and power-architecture risks associated with large AI campuses.
SK Telecom (SKT) and Hyosung Heavy Industries signed a strategic partnership MOU on November 16 at SKT Tower in central Seoul, establishing a framework for cooperation on gigawatt-class AI data center development.
The companies plan to coordinate in advance on the manufacturing and delivery of long-lead critical equipment for 345 kV substations. They will also jointly evaluate and demonstrate 800 V DC distribution technology, share operational and maintenance expertise for extra-high-voltage substation infrastructure, and identify potential new AI data center construction projects.
For large AI campuses, grid-side and on-site electrical infrastructure can become a critical path alongside data hall construction and IT deployment. The agreement is therefore aimed at building a more resilient procurement structure for key power equipment and at assessing a next-generation power-distribution approach for high-density AI loads.
SKT has previously announced a plan to build AI data centers with an aggregate scale of up to 15 GW by 2035. This is a stated future target for total planned AI data center development, rather than operational or commissioned capacity.
The MOU does not confirm an EPC award, equipment order, site, CAPEX commitment, construction schedule, or a specific data center project. Its reference to “gigawatt-class” AI data centers does not assign a numerical capacity to any individual development.
The MOU targets two material constraints on large AI data center development: access to long-lead high-voltage equipment and power-conversion efficiency within the facility. Pre-planning transformer and other critical-equipment supply could reduce schedule risk for large campuses, while 800 V DC trials may support more efficient power architectures for high-density loads.