South Korea AI Data Center Pipeline Advances, With Ulsan Project Targeting 103 MW by 2029
DataNews Editorial Team
US technology companies and Korean partners are advancing several AI data center initiatives in South Korea, although many remain in planning, negotiation or pre-construction stages. The most defined project is SK Group and AWS’s Ulsan facility, which is targeting a 41 MW partial launch by the end of 2027 and expansion to 103 MW in February 2029.
- SK Group and AWS plan a 41 MW partial launch in Ulsan by the end of 2027, expanding to 103 MW in February 2029.
- Microsoft’s third Busan data center project is advancing, but construction commencement remains unconfirmed.
- OpenAI’s discussions with Samsung and SK do not yet include a confirmed site.
- Anthropic and SK Telecom’s gigawatt-scale AI data center initiative lacks disclosed capacity, location and schedule details.
- NAVER plans a 55 MW AI computing infrastructure launch in the first half of 2027, beginning from its Sejong data center.
SK Group and AWS are building an AI data center at the Ulsan-Mipo National Industrial Complex. The project has the clearest disclosed delivery profile among the current group of South Korean AI infrastructure initiatives: a 41 MW partial launch is planned by the end of 2027, followed by expansion to 103 MW of total project capacity in February 2029.
SK Gas had previously indicated that the Ulsan project could deploy approximately 60,000 GPUs. That figure describes the planned IT equipment scale rather than operating capacity.
Elsewhere, Microsoft is progressing a third data center project in Busan’s Gangseo district, but a formal construction start has not been confirmed. The company completed its first Busan data center in April 2020, while a completion ceremony for a second facility took place in September 2024.
OpenAI is discussing AI data center development options with Samsung and SK, but no final South Korean site has been announced. Haenam and Jangseong have been identified as candidate locations rather than confirmed project sites.
Anthropic and SK Telecom have signed an MOU covering cooperation on a gigawatt-scale AI data center in South Korea. The precise capacity, location and operating timetable have not been disclosed.
NAVER plans to begin a 55 MW AI computing infrastructure deployment in the first half of 2027, using its Sejong data center as the first base. Separately, NAVER has entered into a US$9 billion computing-infrastructure cooperation agreement with Brookfield.
Taken together, the projects could intensify demand for AI-ready campuses, power supply and GPU infrastructure in South Korea. Their maturity varies materially: the Ulsan project has disclosed phased capacity and target dates, while several other initiatives remain subject to unresolved site selection, construction and delivery details.
The initiatives point to growing competition for AI compute infrastructure in South Korea and could increase demand for large sites, grid connections, GPUs and data center construction capacity. However, only a subset of projects has disclosed capacity and delivery milestones, and announced gigawatt-scale ambitions should not be treated as operational capacity.