South Korea’s leading telecom operators advance AI data-center expansion plans
DataNews Editorial Team
SK Telecom, LG Uplus and KT are expanding or planning AI-oriented data-center infrastructure in South Korea as their related businesses reported growth in the third quarter of 2026. The programmes range from data centers under construction to long-term capacity targets, with much of the capacity still planned rather than operational.
- SK Telecom is constructing about 180 MW of data-center capacity across Ulsan and Seoul.
- LG Uplus’s Paju AIDC is planned at roughly 200 MW; its first 50 MW building is scheduled for completion in June 2027.
- KT plans six sites and targets infrastructure capacity above 1 GW by 2031, without disclosed capacity allocations by site.
- SK Telecom’s 15 GW domestic target for 2035 is a long-term strategy, not operating or committed capacity.
- AIDC revenue increased year on year at both SK Telecom and LG Uplus in the third quarter of 2026.
SK Telecom, LG Uplus and KT are positioning AI data centers as a larger part of their infrastructure-growth strategies, pairing reported growth in AI- and data-center-related revenue with new construction and expansion plans in South Korea.
SK Telecom is building data centers in Ulsan and Seoul with combined capacity of about 180 MW. Separately, the company has set a long-term target to expand its total data-center capacity in South Korea to 15 GW by 2035. That figure is a strategic target, not commissioned capacity, and no implementation phases, CAPEX or power-supply arrangements were disclosed.
LG Uplus is developing a roughly 200 MW AI data center in Paju, Gyeonggi Province, comprising four buildings. Its first 50 MW building has secured customers and is scheduled for completion in June 2027. LG Uplus plans to bring the four buildings online sequentially by 2028; the 50 MW figure applies to the first phase rather than the full Paju development.
KT plans to commission six data-center sites sequentially, including facilities in Bucheon, Gaebong, Gunsan, Yongin and Ansan, and aims to expand infrastructure capacity beyond 1 GW by 2031. The available information does not allocate capacity across individual sites or specify the development status of each location.
The operators’ reported commercial performance provides the immediate backdrop for the expansion programmes. SK Telecom’s AIDC revenue rose 6.2% year on year to KRW126.1 billion in the third quarter of 2026. LG Uplus’s AIDC revenue increased 27.7% to KRW131.7 billion. KT and KT Cloud reported combined AX revenue of KRW393.3 billion, up 9.8% year on year, although AX is a broader category than data-center activity alone.
Taken together, the plans could reinforce the development of South Korea’s AI-oriented data-center market. In the near term, they could support demand for sites, colocation, design, construction and operations. Over the longer term, the scale and timing of the proposals increase the importance of grid-capacity availability and the operators’ ability to execute their stated commissioning schedules.
The parallel build-out by South Korea’s three largest telecom operators could deepen the domestic market for AI-oriented data centers and support demand for data-center construction, colocation, power and network infrastructure, and operating services. Execution will depend on delivery of the stated development schedules and the availability of grid capacity.