TECO, GMI Cloud and KSDI Plan 6.4 MW Modular AI Data Center in Kagoshima
DataNews Editorial Team
TECO Electric & Machinery has announced plans to develop a modular AI data center in Satsumasendai, Kagoshima Prefecture, with GMI Cloud and KSDI. The first 6.4 MW phase is planned for completion in 2027, with a targeted nine-month delivery period.
- The announced first phase is a 6.4 MW modular AI data center planned for completion in 2027.
- TECO is responsible for design, electrical and mechanical systems integration, and technical support.
- The project carries a nine-month target delivery period for the first phase.
- Power, cooling, connectivity and server equipment are intended to be integrated within the first-phase deployment.
- The cited 350 MW figure is a future operational-capacity target, not confirmed capacity for the site or its initial phase.
TECO Electric & Machinery, GMI Cloud and KSDI are jointly developing an AI Factory in Satsumasendai, Kagoshima Prefecture, Japan, centred on a modular AI data center.
The first phase is planned as a 6.4 MW modular facility, with completion targeted for 2027. TECO said the project has a target delivery period of nine months. Both the schedule and completion date are planned parameters rather than evidence of completed construction.
TECO’s scope includes design, integration of electrical and mechanical systems, and technical support. The first phase is expected to integrate power infrastructure, cooling, connectivity and server equipment, positioning the contractor as an infrastructure integrator rather than solely an equipment supplier.
To support local execution and technical service in Japan, TECO has also signed a tripartite memorandum of understanding with Shinetsu Science Industry Co., Ltd. and Kraftia.
For the market, the development could illustrate how modular construction and pre-integrated power and cooling systems can shorten delivery cycles for AI-oriented capacity. TECO has referenced a goal of pursuing 350 MW of operational capacity during subsequent development, but the available information does not establish this as approved campus capacity, contracted capacity, or capacity under construction. It should not be treated as capacity of the 6.4 MW first phase.
The project illustrates the use of modular delivery and integrated power, cooling and MEP systems to accelerate AI infrastructure deployment. TECO’s stated 350 MW operational-capacity ambition signals a broader potential pipeline, but it is a target for future expansion rather than confirmed capacity for this site or its first phase.