UPM receives permit to convert former Kaukas paper mill into planned 250 MW data center
DataNews Editorial Team
UPM has received a construction permit to convert its former Kaukas paper mill in Lappeenranta, Finland, into a planned data center with 250 MW of stated total project capacity. The work is set to include refurbishment of existing buildings and demolition of surplus structures.
- UPM has received a construction permit for a planned 250 MW data center at the former Kaukas paper mill in Lappeenranta.
- The redevelopment includes refurbishing existing buildings and demolishing unused structures.
- The 250 MW figure is stated planned total-project capacity, not commissioned capacity.
- Other proposed projects in the Lappeenranta area include 480 MW for 3 Flash Finland Oy and 310 MW for Nebius; they are separate developments.
- Construction timing, investment, power-supply arrangements and the future operator remain undisclosed.
UPM has secured permission for construction work to repurpose the former Kaukas paper mill site in Lappeenranta, Finland, as a planned data center. The project’s stated total capacity is 250 MW.
The redevelopment plan calls for repair and reconstruction of existing buildings, alongside the removal of structures no longer required. Paper production at the Kaukas site ceased in late 2025, and the last paper machine was dismantled in 2026.
For data-center developers, the project is an example of a large-scale industrial brownfield conversion rather than a greenfield campus build. Retired industrial sites can potentially offer established land parcels, utility infrastructure and grid connections. However, the available information does not confirm the condition, capacity or suitability of those assets for a 250 MW data-center load.
Lappeenranta is also associated with separate proposed data-center projects: a 480 MW total-project-capacity development by 3 Flash Finland Oy in the Huhhansuo area and a 310 MW total-project-capacity project by Nebius on the southwestern outskirts of the city. These capacities relate to distinct projects and should not be aggregated as capacity of the UPM development.
The concentration of proposed capacity could indicate increasing competition for suitable sites and power-system infrastructure in the area. Delivery schedules, investment volumes, the future data-center operator, financing structure, power-supply parameters and technical configuration for the UPM project have not been disclosed.
The project points to the potential reuse of retired industrial sites for large-scale data-center development. Such conversions may be able to draw on existing industrial land, utility infrastructure and grid connections, although the source does not confirm their suitability or available capacity for the proposed facility. Separate large data-center projects cited in the Lappeenranta area also suggest growing demand for sites and power-network infrastructure, but neither their delivery nor the required power availability is confirmed.
- — / November 14, 2026 · RussianSource →