US data-center construction costs rose 13% in 2026 as power constraints tighten
DataNews Editorial Team
US data-center construction costs increased 13% year on year in 2026, according to Turner & Townsend, as AI-infrastructure investment intensified competition for power, skilled labor and construction materials. The firm expects cost growth to moderate to 6–10% in 2027.
- US data-center construction costs rose 13% year on year in 2026, according to Turner & Townsend.
- Power supply was identified as a significant project-completion obstacle by about 56% of surveyed industry professionals.
- More than half of respondents said grid interconnection typically requires one to two years; nearly one-third reported waits of more than two years.
- For a standard 60 MW project, cited construction costs were $15.01/W in Silicon Valley and $10.51/W in Dallas.
- Turner & Townsend expects US cost growth to slow to 6–10% in 2027.
Turner & Townsend estimates that US data-center construction costs rose 13% year on year in 2026—more than twice the global rate and roughly three times the average annual increase of the preceding decade.
The cost pressure reflects competition for electricity supply, qualified labor and construction materials, alongside the risk premium associated with compressed project schedules. Turner & Townsend’s research covered more than 500 active or recently completed projects across 62 markets and included a survey of around 400 industry professionals.
Power availability emerged as a central delivery constraint. About 56% of respondents identified securing electricity supply as a significant obstacle to completing data-center projects. More than half said utility grid interconnection typically takes one to two years, while nearly one-third reported waits exceeding two years.
Regional construction economics also remain materially different. For a standard 60 MW data-center project, Turner & Townsend put construction cost at $15.01/W in Silicon Valley, compared with $10.51/W in Dallas. This differential could increase the importance of site selection in the economics of new capacity, particularly for developers balancing rapid deployment requirements against power and labor constraints.
Turner & Townsend forecasts US data-center construction-cost growth of 6–10% in 2027. While that would represent a slower rate than in 2026, it would not necessarily remove the structural constraints around power procurement, grid interconnection and specialist labor that are shaping AI-infrastructure delivery.
Higher construction costs increase delivery risk for AI-oriented data-center projects, particularly where grid interconnection capacity and specialist labor are constrained. The findings suggest that power availability and connection lead times could constrain compute expansion as materially as access to capital.